Negrellisteg
Initial situation and concept
The Negrellisteg leads across the wide track field near the main station in Zurich. Here, the pedestrian bridge creates an elegant connection between two city districts that were previously separated by the track field. On one side, the generously modernized Kreis 4 is growing, and on the opposite side, the industrial and residential district Kreis 5 is pulsating.
The architecture of the bridge opens up a unique perspective of the urban area on both sides of the bridge when crossing the densely trafficked track field. To enable this view, the project planners chose transparent elements for the bridge structure above the walkway. This leaves the field of vision for pedestrians largely unobstructed despite the protective parapet.
In order to consistently unfold this transparent aesthetic, Jakob Rope Systems was allowed to integrate the Webnet micro stainless steel mesh system for the bridge construction project. The planners on this bridge construction project were: Conzett Bronzini Partner (Chur) as lead civil engineers, Diggelmann + Partner (Bern) as civil engineers for structural design and 10:8 Architekten (Zürich). The construction at the Negrellisteg was carried out by the Ticino-based steel construction company Officine Ghidoni SA as general contractor. In October 2021, the completed Negrellisteg received the Swiss Prix Acier 2021 award for its elegant and functional steel structure.
Construction and implementation
The parapets on the deck of the bridge are equipped with a dense stainless steel mesh. Above the parapets, the installation of an overthrow protection was required, which continues the transparent design in a meaningful way. An ideal application for Webnet micro.
The flexible and transparent net system was flexibly adapted by Jakob Rope Systems in a wide range of rope diameters and mesh sizes as required. Webnet micro with a mesh size of 35 millimeters was chosen as overthrow protection on the Negrellisteg. On both sides of the bridge, 14 net panels each made of Webnet micro were installed. With a net height of 1.40 meters, they extend the parapet below to a total height of 2.20 meters – without restricting the pedestrians' field of vision too much. The net panels are tensioned by individual centerboard supports, between which horizontal and vertical edge ropes (Ø 8 mm, stainless steel, 6 × 7+ WC) are installed.
Technical details
Application
Anti-throw protection on crossing over railway line
Products
Webnet Micro (rope diameter 1,5 mm, mesh aperture 35 mm), net area 370 m2, net length per side 132 m, 14 nets per side (each between 8.50 m and 10 m long, 1.40 m high)
Edge ropes (diameter 8 mm, 6 × 7 + WC)
Services
Manufacturing and delivery, installation instructions and inspection of the rope and net structure
Implementation
2021
Project partner
Client: SBB Real Estate; City of Zurich, Department of Civil Engineering
Bridge Engineering/Architecture – ARGE Negrellisteg: Conzett Bronzini Partner, Chur; Diggelmann+Partner, Bern; 10:8 Architekten, Zurich
Steel Construction Contractor: Officine Ghidoni, Riazzino