Initial situation and concept:
The central building of the St. Josef Foundation in Bremgarten (AG) is being fitted with impressive vertical greenery. Climbing plants will grow along vertical climbing ropes from both above and below, creating interesting green structures.
Jakob Rope Systems was commissioned to manufacture and install the climbing structures in the fall of 2024. Our fitters Stefan and Nico were on hand to install the ropes and tension rod systems. Both are trained specialists for working at height on suspended ropes.
Jakob products and services:
53 Forte M16 tension rod systems (lengths up to 2.5 m) mounted as bracing on flat roof
53 vertical ropes ø 10 mm with fork pressed / fork with turnbuckle M16 (lengths up to 22 m) mounted as climbing ropes
53 vertical ropes ø 10 mm with fork pressed / fork with turnbuckle M16 (lengths up to 3 m) mounted as bracing ropes below
Pre-dimensioning of ropes and tension rods
Installation with work at height: Our specially trained fitters carried out the installation on the hanging ropes
Fire protection: Implementation in accordance with VKF recommendations with a distance of 0.6 m from the facade. Our stainless steel ropes and components are non-flammable
Project partners:
Metal construction (planning, production, assembly): Fehrtech AG
Landscaping (planning, design): Ingold Gartenbau AG
Planting: Emil Huber AG